Get $1,000 off a full roof replacementSee offer terms. Get started
Roofing Resources
Blog

How to Plan a Roof Tear-Off: Bins, Tarps, Weather and Protecting the Property

Most tear-off problems are decided before anyone climbs a ladder: where the bin goes, what is covered, and how much roof gets opened in a day.

  • Advanced
  • Half a day of planning and setup
  • Updated

The short answer

Plan a tear-off by sizing the bin to the roof (about 1 ton of debris per 7 squares of single-layer shingles), placing it under the eave where you can throw or chute straight in, covering landscaping and vents, checking older roofs for asbestos before disturbing them, and only stripping as much roof as can be dried in before nightfall. Check the forecast and warn the neighbours.

A tear-off is not just taking shingles off. It is opening a house to the weather, dropping hundreds of kilograms of debris a minute, and leaving a roof exposed at the end of each day. The work that goes right is almost always the work that was thought through first: where the bin sits, what is covered, which sections get stripped, and what the forecast says for the next three days.

Planning also decides what you learn before it is too late. The layers on the roof, the condition of the deck, whether the old roofing contains asbestos and whether the driveway will take a loaded bin are all things to find out before the crew or the homeowner starts. In the Fraser Valley, where a dry morning can turn into a heavy rain in the afternoon, the plan for drying in matters as much as the plan for stripping.

This guide covers the planning and setup. The stripping itself is in how to tear off an old shingle roof, and protecting the open roof at night is in how to dry in and tarp a roof overnight.

Tools

  • Tape measure
  • Plywood sheets or lumber for protecting the bin landing and walkways
  • Heavy tarps, 10 by 12 feet or larger
  • Magnetic sweeper
  • Ladder with stand-offs and a ladder stabilizer
  • Roofing shovels
  • Roof anchors and fall protection gear
  • Leaf blower

Materials

  • Disposal bin sized to the roof, with a removable gate or side door if possible
  • Plywood to spread the load of the bin on a driveway
  • Poly sheeting and painter's tape for vents and openings
  • Tarps for shrubs, patios and air conditioners
  • Temporary roofing tarps and lumber for drying in
  • Plastic sheeting for the attic floor if the ceiling below is vulnerable

Safety first

  • Fall protection is required where a fall could be 3 metres (about 10 feet) or more. Decide the anchor points during planning, not on the roof.
  • Roofs built before about 1990 may contain asbestos in shingles, felts, flashing cement or vent materials. Identify and test before anything is broken up, and follow WorkSafeBC rules if it is present.
  • Falling debris is a hazard to everyone on the ground. Mark a no-go zone along the eaves and keep kids and pets indoors.
  • Do not stack bundles or debris so that they overload one part of the roof. A loaded roof edge is a fall and a collapse risk.

Step by Step

  1. Step 1: Walk the roof and the property and record what you find

    Check how many layers of roofing are on the roof by looking at the edge at the eaves and rake. Two layers means roughly twice the debris and weight, and a much harder day. Measure the roof in squares (100 square feet each). A typical house of 25 to 35 squares sets the bin size and the crew size.

    Note what is at the edge of the ground, too. Look for overhead power lines, a septic tank or field where the bin cannot sit, a soft lawn, a low-hanging tree, a pool, and a neighbour's property line. Then look at the roof itself for skylights, chimneys and vents that need protecting or that will be flashed again later.

  2. Step 2: Check for asbestos on older roofs before you disturb anything

    Asbestos was used in some older roofing materials, including certain shingles, felts, flashing cements and mastics. You cannot identify it by looking. WorkSafeBC requires that hazardous materials, asbestos included, be identified before demolition or renovation work disturbs them, and that removal is done by properly trained workers when it is present. Breaking, cutting or grinding an asbestos-containing roof releases fibres.

    The practical step is to have samples taken and analysed by an accredited lab before the job starts. The result decides the plan: normal tear-off if it is clear, or an asbestos abatement process with the required notifications and disposal if it is not. Check the current WorkSafeBC requirements for homeowners and contractors before you begin.

    Watch out: Never break up, sweep or bin suspect roofing before it has been tested. Once fibres are airborne, the cleanup is far more expensive than the test.

  3. Step 3: Size the bin and place it under the eave

    A single layer of asphalt shingles and underlayment weighs roughly 2.5 to 3 pounds per square foot for debris, about 250 to 300 pounds per square. A 30 square roof is therefore about 4 tons, and a second layer doubles it. Most bin companies rate bins by cubic yards and limit weight, so ask for one sized for shingle weight, not volume.

    Place the bin where debris lands in it directly. A bin 1 to 2 feet from the eave, on the driveway or a pad, lets you work downhill with a shovel. Put plywood sheets under the bin's wheels or feet to protect the driveway, and keep the bin away from the trees and overhead lines. If you have a choice, a bin with a drop gate makes loading and sweeping easier.

    • Check the bin's weight limit and the price of overage before you order.
    • Leave room on the street for the truck to pick it up.
    • Get a municipal permit if the bin has to sit on the road.
  4. Step 4: Protect landscaping, windows, vents and the house

    Drop tarps or plywood over shrubs and beds along the eaves, and lean plywood against the walls where debris will fall to spare siding and windows. Cover air conditioners and pool equipment completely, because a single nail in a fan or a pump is an expensive repair.

    Inside the house, cover the attic floor and any stored items under the roof if the ceiling is vulnerable, and warn the homeowner that dust and vibration will come through. Block open vents, including bathroom fan ducts and plumbing stacks, with poly and tape so debris does not fall in.

    Tip: Take dated photos of the property before you start. They settle any later question about a scratched driveway or a broken plant.

  5. Step 5: Set up access and fall protection

    Put the ladder on firm, level ground with stand-offs to keep it off gutters, tied off at the top and extending at least 3 feet above the edge. Install roof anchors at the ridge into rafters while the roof is still intact, using the method in how to install a roof anchor.

    Plan the path workers take to reach each section so nobody crosses the open areas. A roof stripped to bare plywood is slippery in the wet, and the walk a roof safely guide covers the footing and pitch limits.

  6. Step 6: Check the weather and set how much you strip a day

    Rain is the one thing that turns a tear-off into an insurance claim. Check a forecast the night before and the morning of, and watch for wind, which makes tarping dangerous. If the forecast is uncertain, strip a smaller section, leave a day of margin, or wait. In the Fraser Valley the rain windows in fall and spring are short, so the plan is to work in sections.

    Strip whole sections, such as one slope or half a slope, not random patches. The rule is that every part of the roof opened in the morning must be covered by evening, either with new underlayment and ice and water shield or with tarps. The method is in how to dry in and tarp a roof overnight.

  7. Step 7: Talk to the neighbours and the homeowner

    Give neighbours notice of the start date, the hours and the expected noise and dust. Ask them to move vehicles off the street near the bin and to keep windows closed on the day. A short heads-up avoids most complaints and makes the jobsite easier to work.

    Agree with the homeowner on where the crew parks, which door they use for washrooms, where pets and children stay, and whether the attic needs to be cleared. Check the municipal bylaw for noise hours, because starting too early can shut a job down.

  8. Step 8: Stage materials and equipment before the tear-off

    Having the new materials on site before stripping means the roof can be dried in before nightfall. Check that the quantities match the plan, including spare plywood sheets for deck repairs that turn up after stripping. Loading the roof is covered in how to load shingle bundles. Spread bundles across rafters, never stacked at one spot.

Fraser Valley Notes

Fall and spring tear-offs face the longest wet spells, and atmospheric river events can drop a month of rain in a few days. Build a day of margin into every schedule and have tarps and lumber ready for the morning after. Summer work is easier on the weather side but hot decks are hard on the crew, so start early and plan for breaks. Older houses in Chilliwack, Abbotsford and Hope often have cedar shake or old plank decking, which changes the plan for the deck (see how to resheet over plank decking).

Questions to Answer Before Day One

  • How many layers are on the roof, and is asbestos testing done?
  • Where does the bin go, and will the driveway take its weight?
  • What gets covered: plants, vents, air conditioners, windows, the attic floor?
  • What are the anchor points, and who is tied off where?
  • What does the forecast say for the next three days, and what is the plan if it changes?
  • Are the new materials on site, including spare plywood?

Common Mistakes

  • Undersized bin. A bin that fills halfway through a roof stops the job, and debris piled on the ground has to be hand-loaded later.
  • Bin on a soft or unprotected driveway. The weight cracks asphalt and sinks into lawn. Plywood under the feet spreads the load.
  • Stripping more roof than can be covered. An open slope at dusk with rain coming is how ceilings and insulation get soaked.
  • Skipping the asbestos question on an older roof. Disturbing suspect material without a test can expose workers and turn a normal job into an abatement.
  • No protection for landscaping and equipment. Nails in a lawn, a cracked window or a damaged air conditioner cost more than the tarps would have.
  • No plan for the neighbours. An unannounced start with a bin blocking the street turns small friction into formal complaints.

When to Call a Professional

If the roof is steep, has two or more layers, is over a finished attic, or was built before about 1990 and has not been tested for asbestos, it is time for a roofing contractor. The job involves falls, heavy debris, weather exposure and possible hazardous materials, all at once.

A contractor will also handle bin permits, disposal, deck repairs and the clean-up. Get the tear-off, disposal and deck repair terms in writing so nothing is left to be decided on the roof.

Fraser Roofing does free roof inspections across the Fraser Valley, from Hope to Abbotsford. See our Roof Replacement service or the towns we cover.

How to Plan a Roof Tear-Off: Questions

What size dumpster do I need for a roof tear-off?

Bins are sold by cubic yards but shingles are heavy, so weight matters more than volume. Single-layer asphalt shingles weigh roughly 250 to 300 pounds per square, so a 30 square roof is about 4 tons. Most houses use a 14 to 20 yard bin with a weight allowance. A second layer of shingles roughly doubles the load, so tell the bin company how many layers there are.

How do I protect my yard during a roof replacement?

Cover shrubs and flower beds with tarps or plywood along the eaves, lean plywood against siding and windows where debris will fall, and cover air conditioners and pool equipment. Place the bin on plywood to protect the driveway. After the job, a magnetic sweeper on the lawn and driveway picks up the nails that miss the bin.

Is it OK to tear off a roof if rain is in the forecast?

Only a section small enough to be covered before the rain arrives. Every opened area needs underlayment or tarps by the end of the day. If heavy rain is forecast in the next day or two, or the wind is strong enough to make tarping unsafe, wait. Water getting into the attic can soak insulation and ceilings quickly.

Do I need to test for asbestos before a roof tear-off?

Asbestos can be present in some roofing products on older buildings, typically those built before about 1990, and it cannot be identified by sight. WorkSafeBC requires hazardous materials to be identified before demolition or renovation disturbs them. Having suspect materials tested by an accredited lab before tear-off is the safe route, and the result decides how the job must be run.

How long does a roof tear-off take?

A typical single layer roof of 25 to 35 squares is usually stripped in one day by a crew, and often dried in before nightfall. Steeper roofs, second layers, plank decking and deck repairs stretch that. Weather is the main variable, so schedules should allow extra days, especially in fall and winter.

Related Guides

How to Tear Off an Old Shingle RoofTear off a shingle roof by working from the ridge down with a shingle shovel or fork, sliding the tool under the shingles to break the nails loose and throwing debris into a bin below. Remove the underlayment, drip edge and old flashing, pull or hammer flat every leftover nail, and sweep the deck and the ground with a magnet. Strip only what can be covered the same evening.How to Inspect a Roof Deck for RotInspect a roof deck after tear-off by walking every panel, pressing with a screwdriver and your weight to find soft spots, checking the underside from the attic for stains and daylight, and looking for delaminated plywood, crumbling edges, deflection between rafters and loose or rusted fasteners. Replace any panel that is soft, delaminated or stained through, cutting back to the centre of a rafter.How to Dry In and Tarp a Roof OvernightDry in an open roof by covering bare deck before nightfall with self-adhered membrane or properly lapped underlayment, taped and capped at the edges, or with heavy tarps over the ridge and fastened to lumber strips, not through the tarp alone. Overlap tarps from the ridge down, weigh and batten them against wind, close off open edges and penetrations, and check the forecast before stripping any section.How to Install Ice and Water ShieldInstall ice and water shield on a clean, dry deck, peeling the release film in sections and pressing the membrane flat without wrinkles, starting at the eave over the drip edge. Where the BC Building Code requires eave protection on a shingle roof, it runs at least 900 mm (about 3 feet) up the slope and to a line at least 300 mm (about 12 inches) inside the inner face of the exterior wall. Common laps are 3 inches at the sides and 6 inches at the ends.How to Install a Roof AnchorA temporary roof anchor is a steel plate with a D-ring, nailed through the shingles into the rafters near the ridge so a lifeline can clip to it. Find the rafter, fit the anchor in line with the work area, drive every specified fastener into solid framing, and never rely on the sheathing alone. Fall arrest anchors must be rated for at least 22 kN (5,000 lb) unless an engineer designs otherwise.How to Walk a Roof SafelyWalk a roof only when it is dry, free of frost and moss, and in daylight. Wear soft-soled boots with good tread, stay on the lowest pitch you can, keep your weight over your feet and use three points of contact on steeper slopes. Always use fall protection on steep pitches or where a fall could be 3 metres (10 feet) or more.How to Load and Stage Shingle Bundles on a RoofLoad bundles in small stacks spread across several rafters or trusses, near the ridge and over bearing walls where possible. A square of laminated shingles weighs roughly 200 to 250 pounds, so keep stacks small. Lay bundles flat with the long edge parallel to the ridge, or straddle them over the ridge on steeper roofs, and block them so they cannot slide.

All Tear-Off, Decking and Underlayment guides|The full How-To Library

This guide is general education. Always follow the product manufacturer's installation instructions, the BC Building Code and WorkSafeBC requirements, which take priority over anything written here.

Want someone to look at your roof?

Kory & Johnny have roofed homes across the Fraser Valley since 2016. Free inspections, honest estimates, no pressure.

604-728-0146Text UsEmail

Serving Hope, Agassiz, Chilliwack, Rosedale, Abbotsford & the entire Fraser Valley

$1,000 off applies to full roof replacements of 3,000 sq ft or more. Cannot be combined with other offers or previously placed orders. Not valid on partial jobs, repairs, or insurance claims.

We use cookies and the Meta Pixel. Meta receives information about your visit and uses it to measure our ads and show you ads. Decline turns it off. Privacy policy