How to Install Ice and Water Shield on Eaves, Valleys and Penetrations
A self-adhering waterproof membrane that seals around nails. Where it goes, how far up it runs, and how to lay it without wrinkles.
- Advanced
- 2 to 4 hours for a typical roof
- Updated
The short answer
Install ice and water shield on a clean, dry deck, peeling the release film in sections and pressing the membrane flat without wrinkles, starting at the eave over the drip edge. Where the BC Building Code requires eave protection on a shingle roof, it runs at least 900 mm (about 3 feet) up the slope and to a line at least 300 mm (about 12 inches) inside the inner face of the exterior wall. Common laps are 3 inches at the sides and 6 inches at the ends.
Ice and water shield is a rubberized asphalt membrane with a sticky underside. It bonds to the roof deck and seals around every nail driven through it, so water that is pushed under shingles by an ice dam or wind-driven rain has nowhere to go. It is a backup waterproofing layer, not the roof itself.
It belongs at eaves, valleys, and other places where water is likely to get in. Ice and water shield at the eaves protects against ice dams and wind-driven rain, which the BC Building Code recognises with its eave protection rules. In the Fraser Valley, freeze-thaw cycles at Hope and the canyon, and heavy rain across the valley, make this a sound investment anywhere on a roof with a shallow pitch or long overhangs.
This guide covers laying the membrane. The underlayment that goes over the rest of the deck is covered in how to install synthetic underlayment and how to install felt underlayment. For how the drip edge goes with it, see how to install drip edge. Under metal panels, use a high-temperature membrane, see metal roof underlayment.
Tools
- Hook blade utility knife
- Chalk line
- Tape measure
- Roller or a stiff push broom for pressing the membrane down
- Roofing hammer
- Broom
- Knee pads
Materials
- Self-adhering waterproof roofing membrane in 36 inch rolls
- Primer for cold weather or dusty decks, if the manufacturer calls for it
- Drip edge
- Cap nails or 1 inch roofing nails at the top edge
- Butyl or compatible sealant for terminations
Safety first
- Stay tied off. A membrane with the release film peeled is slick, and film pieces on the deck are a slipping hazard. Gather and bag them.
- Membrane sticks aggressively, including to gloves and clothing. Work with gloves and cut pieces before peeling.
- Do not work on wet or frosty decks. Membrane does not stick to a wet deck and you risk a fall.
- Wear long sleeves in hot weather. Dark membranes can burn skin and get soft and sticky in direct sun.
Step by Step
Step 1: Prepare a clean, dry deck
The membrane only sticks to a clean, dry, smooth surface. Broom off dust and grit, drive down raised nails and remove staples. Do not install over wet or frosty wood. Most manufacturers give a minimum application temperature, commonly around 5 degrees C (40 F), below which the adhesive is slow to bond. In cold weather, a primer or warm storage of the rolls may be needed. Always follow the manufacturer's instructions for your product.
On OSB or dusty decks, prime where the manufacturer calls for it. Check the deck for damage first, using how to inspect a roof deck for rot.
Step 2: Decide how far up the roof it goes
The BC Building Code's eave protection rule for shingle, shake and tile roofs calls for protection from the roof edge a minimum of 900 mm up the slope, to a line not less than 300 mm inside the inner face of the exterior wall. The same article lists exceptions: unheated garages, carports and porches, overhangs longer than 900 mm measured along the slope, asphalt shingles laid by the code's low-slope method, slopes of 1 in 1.5 (8/12) or steeper, and locations with 3,500 or fewer heating degree-days. The code also accepts materials other than self-adhered membrane, such as two plies of No. 15 felt cemented together.
That degree-day exception matters here. The code's own climate table puts Chilliwack at about 2,780 degree-days, Abbotsford at 2,860 and Hope at 3,000, so on much of the valley floor the code does not strictly require eave protection. Do not read that as permission to skip it. Shingle manufacturers commonly call for a leak barrier at the eaves wherever ice dams or backed-up gutters are possible, the code requires their instructions to be followed, and a cold snap after wet snow will back water up at the eave anywhere in the valley. Many roofers in the region lay it on every shingle roof, and your local building department may have its own requirement.
On a house with a typical overhang of 12 to 16 inches, the inside of the wall is about 2 to 3 feet up the slope from the edge, so the 300 mm rule usually means two courses of 36 inch membrane. Ice damming is worst where the roof is shallow, the overhang is long, the attic is warm, and at valleys, so those roofs deserve more.
Tip: Measure from the inside face of the wall, not the outside. Get the real overhang and wall thickness, then snap a line and lay the membrane to it.
Step 3: Start at the eave and fit the drip edge order
At the eaves the drip edge goes on the deck first, and the membrane goes over it, so water runs from the membrane onto the drip edge and out. At the rakes the order is reversed: membrane first, then drip edge over it. Details are in how to install drip edge.
Set the first course so the lower edge sits over the drip edge flange, and trim so the membrane does not hang out beyond the gutter line. Cut the roll to length before peeling.
Step 4: Peel the release film and press the membrane down
Cut a length of roll to the run, plus an inch or two for overhang. Fold it in half lengthways, peel a few feet of film, and position the membrane along the line. Press it down from the centre outward to avoid wrinkles and air pockets, and then peel the rest of the film as you go. Do not stretch it.
Two people work better on long runs. Once it touches the deck it is difficult to reposition, and pulling it up tears the membrane and the top layer of the plywood.
Step 5: Roll or press every inch firmly
Adhesion depends on pressure. Use a J-roller or a stiff broom and work across the width, not just along the length. Pay extra attention to laps and to edges, where lifting begins. Wrinkles and fish-mouths at edges are channels for water, and are cut and patched before shingles go on.
Step 6: Lap each course correctly
Most manufacturers mark the roll with a selvage line for the side lap, commonly 3 inches. End laps are commonly 6 inches and should be staggered from one course to the next, so two end laps do not stack. Upper courses lap over lower ones so that water sheds over the joint. Confirm the lap dimensions against the product's instructions.
If you need to install a second course above the first, it laps onto the first by the side lap width, never under it.
Step 7: Cover the valleys and other high-risk areas
A strip of membrane in the centre of the valley, then the shingles or metal over it, is standard. See how to prep a roof valley. Low-slope areas below about 4/12 pitch and areas where a shingle manufacturer requires full coverage need it across the whole slope. Wall junctions get a strip turned up the wall, as in how to install step flashing, and penetrations get membrane sealed tight around them.
Fold the membrane into inside corners and press it in well, so there is no bridging gap.
Step 8: Finish edges, nail the top and cover with underlayment
The top edge can be tacked with a few nails just above the lap line so it does not slide before the next layer goes on. The field underlayment then laps over the top of the membrane, in shingle fashion. Finish with shingles promptly. Most membrane products carry an exposure limit, and UV over a long exposure can harm the adhesive and the surface.
Where Ice and Water Shield Goes
- Eaves: from the edge at least 900 mm up the slope and 300 mm inside the inner face of the wall, the BC Building Code measure for shingle roofs. Where the code does not require it, it is still recommended.
- Valleys: the full length, centred.
- Around penetrations: chimneys, skylights, pipes and roof-to-wall joints.
- Low slopes: the whole area where the pitch is below the shingle manufacturer's limit for standard underlayment.
- Rakes: many roofers run a strip up the first few feet of the rake edge for wind-driven rain.
Hot Weather, Cold Weather
In summer heat the membrane is soft and sticky, so cut it to length in the shade and handle it carefully. In cold weather the adhesive is slow and the film is stiff. Store rolls somewhere warm, use primer where the manufacturer calls for it, and press the membrane hard. Do not install below the manufacturer's stated minimum temperature.
Common Mistakes
- Stopping at the outside wall line. Water from ice dams backs up past the eave and into the wall. Go at least 300 mm inside the inner face of the wall.
- Installing over wet or dusty wood. The adhesive does not bond, and the membrane slides or lifts.
- Wrinkles and fish-mouths. They make channels for water, and have to be cut out and patched.
- Wrong drip edge order. At the eave the drip edge goes under the membrane, and at the rake it goes over.
- Short laps or stacked end laps. Laps under 3 inches at the sides or 6 inches at the ends leak, and stacked end laps make a weak line.
- Leaving it exposed too long. UV and foot traffic degrade the membrane.
When to Call a Professional
Membrane installation is fast to get wrong and hard to fix, because it does not come up without tearing. If the roof is steep, the eaves are high, or the job includes valleys and penetrations, call a roofing contractor.
If you have ice dams, check the attic insulation and ventilation first, because membrane treats the symptom rather than the cause. See how to deal with an ice dam.
Fraser Roofing does free roof inspections across the Fraser Valley, from Hope to Abbotsford. See our Roof Replacement service or the towns we cover.
How to Install Ice and Water Shield: Questions
How far up the roof should ice and water shield go?
Where the BC Building Code requires eave protection on a shingle roof, it runs from the roof edge at least 900 mm (about 3 feet) up the slope and to a line at least 300 mm (about 12 inches) inside the inner face of the exterior wall. The code exempts some cases, including unheated garages, slopes of 8/12 or steeper and mild areas with 3,500 or fewer heating degree-days, which includes much of the Fraser Valley floor. Not required is not the same as not needed: it is recommended on every shingle roof, because ice dams and backed-up gutters still happen here. Valleys and penetrations also get membrane.
Does ice and water shield go over or under the drip edge?
At the eaves, the drip edge goes on the deck first and the membrane goes over it, so water runs from the membrane onto the drip edge. At the rakes, the membrane goes first and the drip edge goes over it, so wind-driven rain cannot get under the metal. The order is reversed at the two edges.
What temperature can you install ice and water shield?
Most self-adhering membranes need a deck temperature above about 5 degrees C (40 F) for the adhesive to bond, and colder conditions may need primer or warmed rolls. Some low-temperature products work lower. Always check the manufacturer's instructions for your product, and do not apply over wet or frosty wood.
Can you use ice and water shield on the whole roof?
Yes, it can be used across the whole deck, and some roofers do on low slopes, complex roofs or high-value homes. It is more expensive than standard underlayment and does not breathe, so it can trap moisture in some assemblies. Where the whole roof is covered, attic ventilation matters even more.
How long can ice and water shield be left exposed?
It varies by product, typically from a few weeks to a few months of UV exposure before the roofing goes on. Leaving it exposed too long can degrade the surface and reduce adhesion for the layers above. Check the manufacturer's limit on the roll and cover it with underlayment and roofing as soon as practical.
Related Guides
All Tear-Off, Decking and Underlayment guides|The full How-To Library
This guide is general education. Always follow the product manufacturer's installation instructions, the BC Building Code and WorkSafeBC requirements, which take priority over anything written here.
Want someone to look at your roof?
Kory & Johnny have roofed homes across the Fraser Valley since 2016. Free inspections, honest estimates, no pressure.
604-728-0146Text UsEmailServing Hope, Agassiz, Chilliwack, Rosedale, Abbotsford & the entire Fraser Valley