How to Flash TPO Walls, Curbs and Corners: Heights, Corner Patches and Terminations
Where a flat roof meets a wall or a curb, the membrane turns up, the corner is formed from pre-molded pieces, and the top edge is pinned and sealed.
- Professional
- Half a day to 2 days depending on the number of details
- Updated
The short answer
Flash a TPO roof at walls and curbs by running the membrane up at least 8 inches above the roof surface, adhering it to the substrate, welding it to the field sheet with a lap of 1-1/2 inches or more, and terminating the top edge with a fastened bar and sealant under counter flashing or cladding. Corners use pre-molded pieces or formed patches, and every T-joint gets a round patch.
The open field of a flat roof is the easy part. The places where the membrane meets a parapet wall, a curb, an inside corner or an outside corner are where time is spent and where leaks start. Water that reaches the wall runs down it, and whatever the membrane does at the base, it does under that water.
A well-flashed wall has three things: a membrane that turns up far enough to stay above standing water and splash, a corner that is formed from a proper patch or molded piece, and a top edge that is pinned so the membrane cannot sag and sealed so water cannot run behind it. A poorly flashed wall has a fold the weld never reached, a T-joint left open, or sealant doing the job a lap should do.
This guide covers walls, curbs and corners in a TPO system. For the field welds, see how to hot-air weld TPO seams. For curbs specifically, see also how to flash a curb on a flat roof.
Tools
- Hot-air hand welder with 1-1/2 inch nozzle
- Silicone roller and small detail roller
- Rounded-tip probe
- Hook blade utility knife and scissors
- Caulking gun
- Drill or impact driver for termination bar
- Chalk line and tape measure
- Marking pen
Materials
- TPO flashing membrane, reinforced or unreinforced as specified
- Pre-molded inside and outside corners
- Termination bar with fasteners, typically 1 inch wide
- Membrane-compatible sealant
- Contact adhesive or bonding adhesive for vertical surfaces
- Round T-joint patches
- Cover board or plywood substrate on the wall or curb
Safety first
- Flashing work is close to parapets, hatches and open edges. Tie off and keep your footing clear of loose offcuts and adhesive.
- Hand welding vertical surfaces means working with a hot nozzle close to your hands and face. Use heat-resistant gloves and never point the nozzle toward people.
- Contact adhesive and solvent cleaners are flammable. Keep sparks, hot nozzles and open flames away from containers and wet surfaces.
Step by Step
Step 1: Prepare the wall or curb surface
Flash to a sound substrate. On wood-framed walls this is exterior-grade plywood or a cover board. On concrete or masonry, it is a primed, clean, dry surface. Sharp edges, protruding fasteners and mortar ridges cut membrane and are removed. Check that the wall is wide enough to carry the flashing, the termination and whatever covers them.
Install a cant strip at the base where the manufacturer or designer calls for one, so the membrane does not make a sharp 90 degree fold at the roof to wall junction. A cant softens the bend, and it keeps the membrane from being stressed by thermal movement.
Step 2: Set the flashing height
The widely used minimum height for wall and curb flashing is 8 inches above the top of the membrane in the field, measured from where water will actually stand. Some codes, manufacturers and designers require more, and curbs on roofs with snow loads, drifting or low slopes often do. Confirm the requirement on the project documents.
Plan what covers the top edge before you start. The termination is always covered: by counter flashing set into a reglet, by the wall cladding, by coping, or by an overlapping metal flashing. A termination bar left uncovered in the weather is not a finished detail.
Step 3: Adhere the flashing to the vertical surface
Cut a strip of flashing membrane about the height plus at least 2 to 3 inches extra at the base, so it laps onto the field sheet. Flashing is usually unreinforced or reinforced TPO as specified, and is adhered to the wall with the approved adhesive, following the same tack and flash-off rules as in how to install fully adhered TPO.
Roll the membrane up the wall from the bottom to the top, broom or hand roll it tight and keep it plumb. Keep adhesive out of the weld zone at the base, where the flashing will be welded to the field sheet. A flashing adhered over an adhesive-coated lap will not fuse.
Step 4: Weld the flashing to the field sheet
The wall flashing is lapped onto the field membrane at the base. Clean both surfaces, test the welder on scrap and weld the lap with a steady pass, as described in how to hot-air weld TPO seams.
Weld all the way to the end of each piece of flashing. A short unwelded length at the end is a common channel for water, and ends of flashing pieces are where patches and overlaps are needed. Probe the full seam when it has cooled.
Step 5: Form the inside and outside corners
An inside corner is where two walls meet at the roof, or where a wall meets a curb. Weld a pre-molded inside corner over the base and up both walls, and weld the vertical flashing pieces to the tabs. Pre-molded corners are the standard because hand-forming membrane into a tight inside corner leaves folds.
An outside corner is where a wall or curb turns away, for example at the corner of a curb. Use a pre-molded outside corner, or fold the membrane with a formed patch. All corner patches should have rounded edges, because a sharp corner lifts. Weld every edge, then probe. If a preformed piece for your size is not available, the manufacturer can specify a field-formed detail.
Watch out: Do not fold flashing membrane and leave the fold unwelded. A sharp, unwelded fold at an outside corner is a channel that collects water and is the most common flat roof corner leak.
Step 6: Cover every T-joint with a round patch
T-joints happen wherever three layers of membrane meet in a step, such as where a vertical flashing seam lands on a horizontal field seam. The step leaves a tiny channel beside the welded edge that a normal weld cannot close. A patch, typically 3 inches or larger in diameter depending on the manufacturer, covers the step.
Clean the area, round the corners of the patch with scissors, and weld all the way around the edge. Do not try to trowel sealant into a T-joint in place of a patch. A patch is a weld, and sealant is not.
Step 7: Terminate the top edge with a bar and sealant
A typical termination bar is aluminum, about 1 inch wide, fastened through pre-punched slots at roughly 6 to 8 inches on centre into sound substrate, with the top of the membrane pulled tight beneath it. The bar holds the membrane against sag and peeling, and stops wind getting behind it.
Apply a continuous bead of manufacturer-approved sealant along the top edge of the membrane and over the bar, tooled smooth. Sealant here is a secondary barrier. The wall cladding, counter flashing or coping above is the primary one, and it is set over the top so water runs over it and not into it. See how to install counter flashing.
Step 8: Probe and inspect every detail
Go back to every hand weld and probe it along the edge. Look for lifted edges at the tops of corners, for wrinkles in the flashing that have bridged the wall, and for any spot where the membrane has pulled away from the wall between fasteners.
Curbs get extra attention: check that water can leave the upslope side of the curb and is not trapped behind it, and that the curb flashing has a proper counter flashing or cap. See how to flash a curb on a flat roof.
Wall, Curb and Parapet Differences
- Walls: the flashing ends under cladding, a counter flashing or a reglet, so the top edge is protected from rain.
- Curbs: the flashing runs up and over the curb or ends under a metal cap, and the upslope side often needs a cricket so water does not stop behind it.
- Parapets: the membrane may run up, over the top and down the outside, or end at a coping, and it needs an edge detail at the coping. See how to install parapet coping metal.
Movement and Wind
Walls, curbs and roofs move at different rates as temperatures change and as the building settles. A flashing that is stretched tight or bridged over a void tears at the base. Leave the membrane relaxed at the cant, fasten at the top and let the wall legs move.
Wind gets behind loose flashing and lifts it. That is why the top is pinned with a termination bar at regular spacing and why long flashing runs are adhered across their whole surface rather than left loose.
Common Mistakes
- Flashing too low. Less than 8 inches puts the top edge where splash, snow and standing water reach it.
- Unwelded T-joints. They leave a channel at the step between layers that leaks at the first heavy rain.
- Sharp folds at corners. Hand-folded membrane with unwelded creases collects water and opens under movement. Use pre-molded corners.
- Sealant in place of a weld. Caulked laps and patches crack within a few seasons and have no lap to fall back on.
- No termination bar or no cover. An unpinned top edge sags and lets wind and water behind the membrane.
- Adhesive on the weld zone. It prevents fusion at the base of the flashing and leaves a cold seam.
When to Call a Professional
Flashing on a thermoplastic roof needs a hand welder, pre-molded accessories and a tested technique. It is where most leaks originate, and the warranty typically depends on it being done to manufacturer detail drawings. It is not a good place for trial and error.
Call a roofer if a wall or curb flashing is lifting, if a corner shows open edges or if water is staining the wall or ceiling below a roof to wall junction. The repair depends on the exact membrane and needs a matching weldable patch.
Fraser Roofing does free roof inspections across the Fraser Valley, from Hope to Abbotsford. See our Flat Roofing and Torch On service or the towns we cover.
How to Flash TPO Walls, Curbs and Corners: Questions
How high should TPO flashing go up a wall?
The common minimum is 8 inches above the finished roof surface, measured from where water would stand. Some manufacturers, designers and codes require more, particularly on low slopes or where snow drifts build up against a wall. The top edge must also be terminated and covered by counter flashing, cladding or coping, so confirm the exact height on the project documents.
How do you flash an inside corner on a TPO roof?
The standard method is a pre-molded inside corner, which is welded to the base membrane and up the two walls. The wall flashing pieces are then welded to the corner tabs and probed. Hand-folding flashing into a tight inside corner leaves creases that are hard to weld and a common place for leaks.
What is a T-joint patch on a TPO roof?
A T-joint is where the end of one seam meets the side of another, creating a small step between layers. A T-joint patch is a round or oval piece of membrane, usually at least 3 inches across with rounded corners, welded over the junction to cover the step. Most manufacturers require it, and a sealant is not a substitute.
What is a termination bar on a flat roof?
A termination bar is a strip of metal, usually aluminum and about 1 inch wide, fastened through the top edge of the membrane flashing into the wall at about 6 to 8 inches on centre. It holds the membrane against the wall so it cannot sag or be lifted by wind. The bar is sealed and covered by counter flashing or cladding.
Can I use caulk instead of welding TPO flashing?
No. Sealant is used at terminations and small transitions as a secondary barrier only. Laps, corners and T-joints must be heat welded so the membrane is fused into one sheet. A caulked joint cracks and pulls away as the roof moves, and water gets behind it with nothing to stop it.
Related Guides
All TPO and PVC Roofing guides|The full How-To Library
This guide is general education. Always follow the product manufacturer's installation instructions, the BC Building Code and WorkSafeBC requirements, which take priority over anything written here.
Want someone to look at your roof?